Union Jack

Portland Port undertakes £26 million berth development

2 September 2022

Portland Port is embarking on its largest and most ambitious improvement project to date, investing £26 million in a major berth development.

The port has applied for, and had approved, all the necessary permissions to carry out the project.  The development will see the existing Deep Water Berth (DWB) removed, and replaced with a brand new, extended berth. In addition, the works will deliver a 74m extension to the solid quay face of our current primary cruise berth, the Outer Coaling Pier (OCP).

The outcome of the development works will be a brand new DWB with a 250m solid berth face, including a suite of new 150t bollards and with 12m water depth alongside, capable of handling cruise ships up to 350m long.  In addition, OCP will be extended to produce a 250m solid berth face with 11m water depth alongside.  Overall the project will deliver 16,000m2 of additional quayside space and be capable of handling two 350m LOA cruise ships alongside at the same time.

Alex Hayes, Landside General Manager at Portland Port, is overseeing the project and commented that ‘This is a key investment for the port and demonstrates our commitement to the continued development of our infrastructure.  The project has taken a lot of time and planning to take it from its initial conception though to implementation.  There is still a lot of work to be done before the project is complete, however the outcome will be a milestone for the port and its future.’

During the tender process, pre-qualifications were sent out to 20 applicants. Knights Brown are the Managing Contractor with Ramboll undertaking the design work as Principal Designer. Ramboll have used their expertise in the design of quay walls to minimise the tonnage of steel required as well as maximising the use of locally available rock within the works.

The piling works has been awarded to Red 7 Marine.  Red 7 Marine and the port have worked successfully together before, during the construction of the two new dolphins on OCP in 2017.  Red 7 Marine is an experienced marine company which has developed and grown consistently since 1999.

Along with Red 7 Marine, local contractors Barrett Electrical, D&M Groundworks, ESG Trading, Pipefix and Quest Marine will also be involved in supporting the works.

The preparatory works are already underway and, once complete, the development will have used 380,000 tonnes of locally sourced infill material and 4,800 tonnes of steel.  The piling works are due to commence at the beginning of October with the both OCP and DWB being fully operational by 1st May 2023.

The initial surface finish of the quayside will be temporary but heavy duty, to allow for settling, with final surfacing works due to take place between October 2023 and February 2024.

Ian McQuade, Portland Port’s Commercial General Manager said that ‘this development will provide a major and significant enhancement to the port’s capabilities. The new facilities will enable Portland Port to keep pace with the increasing demands from our existing cruise and cargo customers whilst offering the opportunity for future growth. The size of vessels calling at Portland over the last number of years has continued to grow and this investment will enable our business to keep ahead of this trend”.

Ian McQuade added “This is the largest investment Portland Port has ever undertaken and it is a resounding vote of confidence in the business by the company’s owners. The future looks very exciting for the port”.